<title>Handling long, large-footprint computations</title>
|
|
|
|
<h2>Handling long, large-footprint computations</h2>
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
The sequential components of some applications are long
|
|
|
|
(weeks or months) and have a large data "footprint",
|
|
|
|
i.e. their state may be many MB or GB in size.
|
|
|
|
Each component could be represented by a single workunit.
|
|
|
|
However, this has two potential drawbacks.
|
|
|
|
<ul>
|
|
|
|
<li> In the presence of participant fluctuation,
|
|
|
|
the fractions of uncompleted workunits
|
|
|
|
and wasted CPU time increase without bound.
|
|
|
|
<li> If hardware error occurs early in a workunit,
|
|
|
|
the rest of the CPU time is wasted.
|
|
|
|
<li> It's impossible for the project to abort a component
|
|
|
|
(e.g. because another component has a better result).
|
|
|
|
</ul>
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
Alternatively, each component could be subdivided into
|
|
|
|
a number of workunits of bounded average duration (e.g. one day).
|
|
|
|
The avoids the above problems, but it requires the state files
|
|
|
|
to be uploaded frequently, which may impose prohibitive
|
|
|
|
network and storage loads.
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
To solve these problems, BOINC provides a mechanism
|
|
|
|
called <b>work sequences</b>.
|
|
|
|
Each work sequence represents a long, large-footprint component.
|
|
|
|
It consists of a sequence W1, ... Wn of workunits;
|
|
|
|
each workunit has one or more results.
|
|
|
|
BOINC attempts to execute a work sequence
|
|
|
|
entirely on one host, since this minimizes network traffic.
|
|
|
|
However, it will "relocate" a work sequence
|
|
|
|
(i.e. shift it to another host) if
|
|
|
|
<ul>
|
|
|
|
<li> The current host fails or is too slow
|
|
|
|
<li> The current host returns an erroneous result
|
|
|
|
</ul>
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
A work sequence is dynamic;
|
|
|
|
the project back end may extend it depending on the results.
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
The output files of a result in a sequence are classified as
|
|
|
|
<ul>
|
|
|
|
<li> State files: these may be used as input files of
|
|
|
|
later workunits in the sequence.
|
|
|
|
They are typically large.
|
|
|
|
They need not be uploaded.
|
|
|
|
<li> Answer files: these are a high-level summary of
|
|
|
|
the results thus far.
|
|
|
|
They are typically small and are always uploaded.
|
|
|
|
They allow the project to decide whether to extent the sequence.
|
|
|
|
</ul>
|
|
|
|
A result need not have ANY output files;
|
|
|
|
such a result supplies a "heartbeat" telling the
|
|
|
|
server that the host is still working.
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<h3>Creating work sequences</h3>
|
|
|
|
<p>
|
|
|
|
A project creates a work sequence using
|
|
|
|
the <b>create_work</b> utility.
|
|
|
|
This creates an initial sequence, which may be extended later (see below).
|
|
|
|
The sequence has one result per work unit.
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
The results in a sequence typically have the following structure:
|
|
|
|
<ul>
|
|
|
|
<li> Each Nth result generates and uploads an answer file.
|
|
|
|
N may be as small as one if frequent checking (for correctness or
|
|
|
|
comparison with other sequences) is needed.
|
|
|
|
<li> Each result generates a state file,
|
|
|
|
but only every Mth result uploads the file.
|
|
|
|
Some applications might have a "hierarchical state" scheme in which,
|
|
|
|
for example, a large state file is uploaded every 50 results
|
|
|
|
while a smaller state file is uploaded very 10 units.
|
|
|
|
This could reduce wasted CPU for a given level of network traffic.
|
|
|
|
</ul>
|
|
|
|
The decision of whether to use work sequences,
|
|
|
|
and the optimal values of parameters (N, M, and workunit duration)
|
|
|
|
depend on many factors and are left up to the project.
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<h3>Scheduling work sequences</h3>
|
|
|
|
<p>
|
|
|
|
A work sequence is represented in the BOINC database by its first workunit.
|
|
|
|
At a given time each sequence is either unassigned or is
|
|
|
|
assigned to a particular host.
|
|
|
|
Each host keeps track of the sequences it believes are assigned to it.
|
|
|
|
<p>
|
|
|
|
This head workunit contains a "maximum result time";
|
|
|
|
the sequence should only be assigned to hosts that
|
|
|
|
can complete a result in this amount of real time.
|
|
|
|
It also contains a link to the first workunit in the sequence
|
|
|
|
for which no validated result has been received,
|
|
|
|
and to the first workunit that has not been dispatched yet
|
|
|
|
to the assigned host.
|
|
|
|
<p>
|
|
|
|
Each RPC to a BOINC scheduling server includes a list of
|
|
|
|
work sequences assigned to the host.
|
|
|
|
<p>
|
|
|
|
If no work sequences are assigned to the host,
|
|
|
|
the scheduler checks for an unassigned work sequence
|
|
|
|
that the host is fast enough to handle.
|
|
|
|
If there is one, it sends it one or more results from
|
|
|
|
this sequence, and assigns the sequence to the host.
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
Scheduling notes:
|
|
|
|
<li>
|
|
|
|
If the high-water mark allows multiple results to be active,
|
|
|
|
the host can upload result N while processing result N+1.
|
|
|
|
<li>
|
|
|
|
Conceivably there could be cases where a state file upload could
|
|
|
|
be aborted because a newer state file is available.
|
|
|
|
This isn't worth worrying about.
|
|
|
|
<li>
|
|
|
|
This policy limits each host to one sequence; may be want to
|
|
|
|
modify for multiprocessors.
|
|
|
|
</ul>
|
2002-11-03 19:11:05 +00:00
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
For each sequence reportedly assigned to the host,
|
|
|
|
the scheduler checks whether the sequence is still assigned to the host,
|
|
|
|
and if not returns an element telling the host it's no longer assigned.
|
|
|
|
Otherwise, it sends the host additional results from the sequence,
|
|
|
|
up to the limit specified by the request.
|
|
|
|
(Note: if the project has a mix of sequence and non-sequence work,
|
|
|
|
this will starve the non-sequence work for this host.)
|
|
|
|
|
|
|
|
<p>
|
|
|
|
<h3>Ending or extending a work sequence</h3>
|
|
|
|
<p>
|
|
|
|
The project's result-handling program,
|
|
|
|
when it has processed a completed result from a work sequence,
|
|
|
|
may generate additional work units and result in the sequence
|
|
|
|
(perhaps a single additional result that uploads the final state files)
|
|
|
|
or it may specify that the sequence has ended.
|
|
|
|
In the latter case, the scheduler will notify the host
|
|
|
|
that the sequence has ended, removing its assignment.
|
|
|
|
|
|
|
|
<h3>Relocating work sequences</h3>
|
|
|
|
<p>
|
|
|
|
A BOINC daemon process periodically checks for work sequences
|
|
|
|
for which some result, dispatched to the currently assigned host,
|
|
|
|
has missed its deadline.
|
|
|
|
It then deassigns the work sequence,
|
|
|
|
and prepares it for reassignment.
|
|
|
|
This involves the following:
|
|
|
|
<ul>
|
|
|
|
<li> Find the latest workunit Wi in the sequence
|
|
|
|
all of whose input files have been uploaded.
|
|
|
|
<li> Generate a new result for Wi
|
|
|
|
with different output filenames.
|
|
|
|
<li> For each workunit W after Wi in the sequence,
|
|
|
|
create a new workunit W' and a new result R,
|
|
|
|
changing the filenames as needed.
|
|
|
|
<li> Reset the pointers in the head workunit.
|
|
|
|
</ul>
|
|
|
|
This creates a "dead branch" which remains in the database.
|
|
|
|
|
|
|
|
<h3>Redundancy checking for work sequences</h3>
|
|
|
|
<p>
|
|
|
|
Redundancy checking for work sequences requires some additional logic
|
|
|
|
because the corresponding groups of results
|
|
|
|
belong to different workunits.
|
|
|
|
The proposed mechanism is as follows:
|
|
|
|
|
|
|
|
<ul>
|
|
|
|
<li> Several work sequences with identical initial states
|
|
|
|
can be created and assigned to the same <b>work sequence group</b>.
|
|
|
|
One of the sequences is chosen as the "master" and the others
|
|
|
|
are linked to it.
|
|
|
|
|
|
|
|
<li> When results for a minimum quorum of
|
|
|
|
the corresponding workunits in a group
|
|
|
|
(e.g. the 1st workunit in all the groups)
|
|
|
|
have been received, they are compared using the same
|
|
|
|
mechanism as for regular workunits.
|
|
|
|
This is repeated as new results are received until
|
|
|
|
a canonical result is found.
|
|
|
|
|
|
|
|
<li> If all the result are present and there is no canonical result,
|
|
|
|
the project is notified (this shouldn't happen often).
|
|
|
|
|
|
|
|
<li> Whenever an erroneous result is found,
|
|
|
|
the work sequence is deasssigned as described above.
|
|
|
|
</ul>
|
|
|
|
|
|
|
|
Note: this scheme could lead to situations in which
|
|
|
|
a slow host holds up the granting of credit to faster hosts.
|
|
|
|
May want to reassign to faster host in this case.
|
|
|
|
|
|
|
|
<h3>Examples</h3>
|
|
|
|
<p>
|
|
|
|
climateprediction.com (known computation length, large state files).
|
|
|
|
Let's say a simulation takes 6 months.
|
|
|
|
Suppose we want a small
|
2002-11-03 19:11:05 +00:00
|
|
|
progress report from the user every 3 days, so we generate 6*30/3 = 60
|
2002-11-03 23:05:12 +00:00
|
|
|
results per sequence.
|
|
|
|
The scheduling server ensures that each host has
|
2002-11-03 19:11:05 +00:00
|
|
|
at least 2 elements of the sequence at a time, so that it doesn't have
|
2002-11-03 23:05:12 +00:00
|
|
|
to wait for data upload in order to continue.
|
|
|
|
If we want a full state
|
2002-11-03 19:11:05 +00:00
|
|
|
save every 3 weeks, we make every 7th result restartable and set the
|
|
|
|
XML file infos so that the large state files will be uploaded.
|
|
|
|
|
2002-11-03 23:05:12 +00:00
|
|
|
<p>
|
|
|
|
Folding@home (unknown computation length, small state files).
|
|
|
|
We don't know in advance how long a computation will take.
|
|
|
|
The server generates a large group of trajectory sequences,
|
|
|
|
but only creates 2 or 3 results in each sequence.
|
|
|
|
The backend work generator periodically checks how
|
2002-11-03 19:11:05 +00:00
|
|
|
much of each sequence has been completed, and extends any sequences
|
|
|
|
that are nearing completion unless it has been decided to permanently
|
2002-11-03 23:05:12 +00:00
|
|
|
terminate them (i.e. because a more promising trajectory has been found).
|